SNI Culvert Repair

Overview

Project Scope and Purpose

This project was to provide repairs to three separate areas around the main airfield at the San Nicolas Island Naval Outlying Landing Field (NOLF).The three areas needing repair under this contract were: 

Specific Work Details

1. Repair of a large sinkhole at the north end of the main runway. The sinkhole was undermining the airfield pavement and causing potential damage to the airfield. The repair work completed included removal, backfill and compaction of approximately 550 CY of native soils. During the backfilling, cement was mixed with the native soils to ensure long-term stability of the repair area. Work also included removal and replacement of airfield concrete pavement and concrete curbs. 

2. Repair by replacement of approximately 12,000 SF of concrete pavement that was badly damaged and cracked. The pavement is in a parking apron used for loading ordnance and test missiles onto aircraft. Concrete raw materials were shipped to the island along with mixing equipment since there is no permanent batch plant on SNI. The repair included saw cutting and removal of the damaged concrete, grading, and subgrade preparation, placing forms and reinforcing steel, placing concrete, and curing blankets and then finally re-painting the striping on the pavement. During the removal process we were able to identify additional areas needing replacement and at no cost to the Government were able to incorporate these areas into our repair footprint. 

3. Inspection, cleaning, engineering, and repairs to the entire airfield drainage system. This included cleaning and inspection of the existing corrugated metal pipe (CMP) storm drains within the airfield area. We mobilized a vacuum truck and video equipment to the Island to clean and then inspect all the pipes. 

Also included in the work was removal and replacement of several areas of native, endangered grasses. At these locations, the grass was removed from the outfall areas, stored, and maintained at the site and then replaced for re-establishment once the work was completed. Martinez Construction was the prime contractor for this contract and self-performed approximately 44% of the project. In addition to management, safety, and quality control, other self-performed efforts included site superintendent, equipment operators, site preparation, all dirt and earth work, and general labor.

Project Category
Site Utilities & Infrastructure
Project Value
$3,866,277
Project Gallery
No items found.

Discover More Projects

View All

Eagle Pass Bridge

Location:
Eagle Pass, Texas
Type of Work:
Completion Date:
May 2019
Roads, Sites & Civil Improvements

Area 2 Gap Filler

Location:
Southern Border, AZ
Type of Work:
Completion Date:
August 2018
Roads, Sites & Civil Improvements